September 4, 2021

Ballston Sewers – Hardship Exemption Survey

The Town of Ballston is exploring using funds from the ARPA (American Rescue Plan Act) to assist Ballston residents who qualify for the financial hardship exemption […]
August 31, 2021

Sewer Project Status Update

Sewer Project Update 8/31/21 The four contractors all continue to make progress.  Contract #1 is working on Jacob Street and making the directional drill under Lake Hill.  They will […]
June 14, 2021

Sewer Connection Manual

The Ballston Lake sewer connection manual is available as of June 5.   The 16-page PDF document can be opened here.  You may save or print the […]
May 10, 2021

Clean-up Day is a Success

Report – May 1, 2021 Clean Up Day Major Sponsors BLIA / BH-BL BPA Total Registered Participants – 72 (it is believed that this number might […]
January 5, 2021

DEC Seedling Program Opens

January 5, 2021 – DEC Annual Tree and Shrub Seedling Sale is now open More than 50 Species Available from Colonel William F. Fox Memorial Saratoga […]
August 24, 2020

Light Up the Night

Light Up the Night on Ballston Lake! Music this weekend on the south end Sunday – Matt Finn will be playing on Eastside starting at 2:30 […]
August 14, 2020

Quotes from Letters to the Town

Quotations from letters to the town from your neighbors within the sewer district “If  the referendum to accept the grant doesn’t pass, we will still have […]
August 11, 2020

More Information on Ballston Sewers Website

You can find a lot of helpful information in the Ballston Sewers website. On the Home Page is the latest updated information about the project. On […]
August 10, 2020

Fecal Coliform In Buell Heights Tributaries

Email – August 1,2020 As you correctly point to and as the chart illustrates, the sheer numbers ABOVE the statutory limitations communicate a source other than […]